Satpayev Thermal Power Station No. 1 completes winter preparation
In Satpayev, preparations of the city’s thermal power facilities for the 2025–2026 heating season have been completed. All works are proceeding on schedule, and the required fuel reserves have been stockpiled: over 200,000 tonnes of coal and over 430 tonnes of fuel oil.
The total repair budget for Thermal Power Station No. 1 amounted to approximately KZT 2 bln. These funds were allocated to both routine maintenance and large-scale investment projects. Completed works include scheduled maintenance of steam and hot-water boilers, pipeline replacements and installation of new mechanical filtration systems.
A full overhaul of Boiler No. 1 has been completed, while the modernization of Boiler No. 4, costing KZT 227 mln is scheduled for completion by October 20.
In addition, measures to reduce ash emissions have been implemented, including the repair of solid particle removal and treatment systems (scrubbers) and the installation of emulsion units. These environmental upgrades were funded with KZT 448 mln.
By the end of the year, the installation of dirt separators in the heating networks is expected to be completed, alongside repairs of aspiration systems. These projects will improve equipment reliability and ensure stable heat supply during the winter season.
However, the Satpayev district heating network operator, SPTVS LLP, currently has an outstanding debt of over KZT 2 bln to the boiler plant. This financial liability negatively impacts the plant’s ability to fulfill contractual obligations with contractors and hinders the timely execution of preparation works for the heating season.
Heat supply to the municipal networks operated by Satpayev Heating and Water Supply Enterprise LLP is scheduled to begin on October 2.